The brief was to contain radiation caused by X-Ray in the Oncology
unit of a public hospital in Australia. The designers had prepared
documents using very thick walls (1.2 m) and a thick roof slab (1.8
m). The walls and roof were very heavily reinforced using conventional
rebar - in excess of 200 kg/m3 - to control cracking. Very
small cracks were not permitted as tests on previous units had
demonstrated excessive radiation leakage due to cracks in the
concrete. The oncology unit was located in a tropical climate, so heat
of hydration was also a major concern with respect to cracking.
The builder wanted to explore an alternative solution and we
proposed using steel fibre, thus eliminating virtually all the rebar.
We also proposed using precast panels as formwork for the walls which
would form part of the wall thickness. The advantages were;
Reduced construction time as there were no reinforcing bar cages
to build and install
Reduced number of workers on site as there was no formwork nor
rebar to install
Reliable concrete pour and compaction as there were concerns
about ensuring sound concrete towards the bottom of the heavily
reinforced walls
The ready-mix concrete supplier developed an excellent mix that
enabled 40 kg/m3 of hook-end steel fibre 65/60 to be
added. To control heat of hydration and obtain a dense concrete mix
a high proportion of non-cementitious binder was used together with
cement.
The project was a successfully completed and tested using radiation
detection equipment. The new oncology unit easily met the stringent
requirements of the client. This project was completed in 2009 and
set a precedent. We understand that all new oncology units
constructed in Australia since then have adopted fibre reinforced
concrete.
It should be noted, very thick walls and slabs constructed of fibre
reinforced concrete would not only contain radiation but would also
be highly resistant to blast forces and severe impact loads. This is
due to the high energy absorption capacity of FRC compared with
conventionally reinforced concrete.
Plan view of the oncology unit
This diagram shows the maze-like nature
of the oncology unit to avoid radiation leakage through openings.
Wall preparation
A view of the top of the walls about to
be poured. The precast panels acting as lost formwork for
the walls and roof slab are visible. Props have been
placed at the top are propped at the top and mesh has been
placed over the openings as a safety measure to prevent
accidental falls and equipment being dropped.
SFRC being poured in walls
This is the first wall that was poured.
All pours were completed during night-time hours to avoid
the heat of daylight hours in the tropical climate.
Preparation of the roof slab
As the roof slab is very thick there was no need for any
conventional reinforcement, nevertheless a bottom layer of
light mesh was adopted to ease any concerns about tension
capacity of the concrete.
Roof pour under way
A boom lift was utilised to deliver the pumped concrete and
apply compaction equipment. As the SFRC had plasticizer the
slump was quite low and did not require a great deal of
compaction. The "tide marks" on the walls indicate the
concrete staging adopted by the builder.
Finished roof slab