Insitu concrete is levelled using
a vibrating Laser screed Note the form-board (orange) indicating the edge of the slab. Pour sizes are typically 30 m x 30 m or larger. The pour size ratio should not exceed 1:1.5. |
|
Wheel ruts and other depressions are raked and a plastic
membrane is placed on the sub-base just prior to placing the
next batch of concrete. |
|
Concrete is placed directly from the chute of the truck onto
the prepared sub-base. This has the advantage of avoiding
pumping equipment for the concrete and elevated trellises for
equipment such as the Laser screed. |
|
Set-downs for loading docks and other features in the pavement can be readily detailed in steel fibre reinforced slabs | |
Heavy duty finishing equipment is required Note that timing is critical. If the blades work the slab surface too early then fibres will be drawn to the surface making the slab almost unusable. If the blades work the slab too late then a thin layer of fines will not be worked to the surface. |
|
Finished distribution centre |
Projects